Access balcony in Mühlheim, Germany

On the 5.5.2015 the concrete was scabbled. There was however a large island of a black coating residue left behind. On the 19.5.2015 work was carried out with the rapid curing epoxy primer INDUFLOOR-IB1258 at +10°C substrate and 12°C ambient temperature. On the 22.5. ASOCRET-HB-flex and ASO-EZ4-Plus at a mean thickness of 7 cm was installed as a bonded screed laid to falls. Inclusive of site equipment, application of ASOCRET-HB-flex and the installation of ASO-EZ4-Plus, 3 men needed approx. 5 working hours.